Preliminary work starts on fence
In the ever-fluid realm of roadwork maintenance and construction, the State Highway Administration confirmed this week that preliminary work on both the median fence and repaving of Coastal Highway from 62nd Street south to 26th Street would begin this week, with actual “shovels in the dirt” work to start in early November.The repaving project is a continuation of the program to resurface the entire 10-mile stretch of Ocean City’s strip, begun last March, from the Delaware line south to 62nd Street. The goal is, as always, to complete the resurfacing before Memorial Day and the start of the summer season.
The median fence will come first. That will include some electrical work to install LED lighting along the barrier to increase visibility.
Charlie Gischlar, media relations manager for the SHA, said completing the fence is Phase I on the project.
“Also in Phase I, crews will lengthen the left turn lane from northbound Coastal Highway to 52nd Street. Doing this will help to improve intersection operations by providing additional vehicle storage for turning motorists,” he said.
More
Appear first on Us News
By ABC News
That's Articles Preliminary work starts on fence
That's an article Preliminary work starts on fence This time, hopefully can benefit for you all. Okay, see you in other article posting.
You are now reading the article Preliminary work starts on fence link https://abconnews.blogspot.com/2017/10/preliminary-work-starts-on-fence.html